Pepper Hill HOA, Concord - 28 units 2006: Renovation of exterior balconies ...Approx. $250,000
Belardo Terrace HOA, Greenbrae - 36 units
2000: Structural repairs of water-damaged glu-lam beams
... Approx. $150,000
2006: Renovation of exterior balconies
... Approx. $200,000
Boyd Court HOA, San Rafael - 25 units
2005: Interior inspections; Repairs due to building settlement
... Approx. $50,000
Headlands II HOA, Sausalito - 96 units
1998: Re-siding with cedar shingles, plus seismic upgrades
... Approx. $2.5 million
2004-2006: Re-roofing, and replacement of decks and stairways
... Approx. $2.2 million
|
Post International HOA, San Francisco - 72 units
2005: Waterproofing of various concrete structures
...Approx. $66,000
Redwood Village HOA, Santa Rosa
2004: Fire restoration of 6-unit building
...Approx. $300,000
Shelter Ridge HOA, Mill Valley - 184 units
1989 - 2006: Siding renovations; Deck replacements; Painting; Drainage; Paving; Misc. consulting & support tasks.
...Cumulative total approx. $4 million
Capital Reserves Studies and Updates
"On the Hill" HOA, Pinole - 140 units
- Original study in 1988 - Updates in 2000 and 2005
Shelter Ridge HOA, Mill Valley - 184 units
- Original study in 1996 - Updates in 1999, 2002 and 2005
|
|
|